Labour Cost & Markup
Crew cost per day and job, plus contractor markup.
Key facts
- Labour = workers × daily wage × days, for each role.
- Overhead covers site supervision, transport, insurance and your office — applied to direct costs.
- Quote = total cost × (1 + markup). A 15% markup is a 13% margin.
- Add a contingency to days or materials for rework and delays.
Worked example
One mason at 1,200 a day and two helpers at 700 for 10 days is 26,000 of labour. With 60,000 of materials and 5,000 of equipment, direct cost is 91,000; 10% overhead makes 100,100. A 15% markup gives a quote of 115,115.