Labour Cost & Markup

Crew cost per day and job, plus contractor markup.

Crew
RoleWorkersDaily wageDaysRemove
Job costs

Key facts

  • Labour = workers × daily wage × days, for each role.
  • Overhead covers site supervision, transport, insurance and your office — applied to direct costs.
  • Quote = total cost × (1 + markup). A 15% markup is a 13% margin.
  • Add a contingency to days or materials for rework and delays.

Worked example

One mason at 1,200 a day and two helpers at 700 for 10 days is 26,000 of labour. With 60,000 of materials and 5,000 of equipment, direct cost is 91,000; 10% overhead makes 100,100. A 15% markup gives a quote of 115,115.