Cement Calculator
Cement bags, sand and aggregate for any concrete mix.
How it's calculated
- Dry volume = wet volume × 1.54 (allows for voids and shrinkage).
- Each material = dry volume × its share of the mix (for M20, 1 + 1.5 + 3 = 5.5 parts).
- One 50 kg bag of cement = 0.0347 m³ (cement density 1,440 kg/m³).
- 1 m³ = 35.31 cubic feet (CFT).
Worked example
A 10 × 10 ft slab, 5 inches thick, is 41.7 CFT (1.18 m³). In M20 the dry volume is 1.82 m³: cement 0.33 m³ ≈ 9.5 bags, sand ≈ 17.5 CFT, aggregate ≈ 35 CFT, before wastage.
FAQ
Which grade should I use for a house slab?
M20 is the usual minimum for RCC slabs, beams and columns in houses. Follow your structural engineer's drawings.
Why 1.54?
Loose sand, aggregate and cement shrink by roughly a third when mixed with water and compacted, so you need about 54% more dry material than the finished volume.
How much water?
Typically a water–cement ratio of 0.45–0.5 by weight for M20: about 22–25 litres per 50 kg bag.
Basis
IS 456 nominal mixes
Estimate only — confirm quantities with your engineer.